Tracking Australia's 13,096 MW data centre pipeline.

DC Watch provides free, public data on Australia's data centre boom.

Seeking approval
8,585 MW
Approved
2,355 MW
Under construction
2,136 MW

What is being built

Nameplate capacity forecast based on project announcements and typical build times.

Australian data centre capacity completed per year, 2020 to 2030 962 megawatts completed to date; 12,676megawatts projected. Forecast begins 2026. Full figures are in the table below.05001,0001,5002,0002,5003,0003,5004,0004,5005,0005,5006,0006,500forecast →← built2690120156220601,7169623,9366,35220202021202220232024202520262027202820292030MW
BuiltForecast

962 MW completed since 2020; 12,676 MW projected to 2030. Unfinished projects are placed in up to two steps. 10 projects where construction has commenced are dated from that start, adding the median 20 months from construction to completion (n=7). The other 32 have not broken ground, so a construction start is estimated first — 8 months from announcement (n=9), 18 months from approval application (n=17), 6 months from approval (n=19) — and the construction leg is added to that. 6 projects (922 MW) are past the date this method predicts and are shown in 2026, which inflates that year. 44 facilities (729 MW) lack the dates needed to place them and are not shown.

View as table
YearBuiltForecastTotalProjects
202026—262
202190—904
2022120—1205
2023156—1564
2024220—2202
202560—602
20262901,4261,71612
2027—9629627
2028—3,9363,93617
2029—6,3526,35211
2030————

Forecast projects, by the year they are projected to complete.

YearProjectOperatorStageCapacity
2026SYD3overdueAirTrunkunder construction400 MW
2026Laverton CampusCDCunder construction400 MW
2026EC3-EC6overdueCDCunder construction270 MW
2026S5NextDCseeking approval104 MW
2026BK3overdueCDCapproved100 MW
2026SYD01 / SYD02overdueDCI Data Centersunder construction70 MW
2026IC3 Super WestoverdueMacquarie Technologyunder construction47 MW
2026Project EchidnaoverdueAmazon Web Servicesapproved35 MW
2026Ferris Road, CobblebankAmazon Web Servicesunder construction0 MW
2027MEL2AirTrunkapproved354 MW
2027S4 Phase 1NextDCunder construction250 MW
2027Maddington CampusCDCapproved200 MW
2027M2 Stage 2NextDCunder construction60 MW
2027Project Southgate Stage 1bFirmusunder construction46 MW
2027Project Southgate Stage 1aFirmusunder construction44 MW
2027SC2NextDCunder construction8 MW
2028M5NextDCseeking approval1,200 MW
2028Western Downs Digital Park Stage 2Zerra DCseeking approval720 MW
2028Marsden Park CampusCDCapproved504 MW
2028Bell BayFirmusapproved288 MW
2028Glendenning Road CampusAmazon Web Servicesapproved235 MW
2028M4NextDCapproved162 MW
2028Project ApolloGoodmanapproved135 MW
2028Project DukeGoodmanapproved120 MW
2028Project PlutoGoodmanapproved100 MW
2028SYD01Goodmanunder construction81 MW
2028Project MarsGoodmanseeking approval81 MW
2028Khartoum RoadStocklandapproved76 MW
2028Unnamed project, Macquarie Park NSWDigital Realtyseeking approval70 MW
2028Gregory HillsAmazon Web Servicesunder construction62 MW
2028Project Southgate Wesley ValeFirmusseeking approval52 MW
2028SYD1 expansionDigiCoapproved46 MW
2028GE1NextDCunder construction4 MW
2029Western Downs Digital Park Stage 1Zerra DCseeking approval1,440 MW
2029Mamre Road Data Centre CampusISPTseeking approval1,000 MW
2029Project Ares Stage 1Energy Northseeking approval1,000 MW
2029BundeyIRENseeking approval800 MW
2029S7NextDCseeking approval700 MW
2029SYD01STACK Infrastructureseeking approval450 MW
2029Project AtlasGoodmanseeking approval348 MW
2029Campbellfield CampusZerra DCseeking approval336 MW
2029KC1CDCseeking approval144 MW
2029BE2CDCseeking approval84 MW
2029M3 ExpansionNextDCseeking approval50 MW

Build times

Every milestone on record for each project, from the approval application through to completion. Align the rows to compare how long each one took.

39 projects of 20 MW or more, past the application stage.

  • Approval sought
  • Approval granted
  • Construction started
  • Completed
  • Elapsed since, to today
  • Projected completion
today2016201620172017201820182019201920202020202120212022202220232023202420242025202520262026202720272028202820292029001y1y2y2y3y3y4y4y5y5y6y6y7y7y8y8yAirTrunk SYD1 Stage 1 — Completed, 90 MWAirTrunk SYD1 Stage 190AirTrunk MEL1 Phase 1 — Completed, 25 MWAirTrunk MEL1 Phase 125NextDC M2 Stage 1 — Completed, 60 MWNextDC M2 Stage 160AirTrunk SYD2 — Completed, 70 MWAirTrunk SYD270NextDC S3 — Completed, 80 MWNextDC S380CDC EC3-EC6 — Construction, 270 MWCDC EC3-EC6270DCI Data Centers SYD01 / SYD02 — Construction, 70 MWDCI Data Centers SYD01 / SYD0270AirTrunk MEL1 Phase 2 — Completed, 25 MWAirTrunk MEL1 Phase 225AirTrunk SYD1 Stage 2 — Completed, 40 MWAirTrunk SYD1 Stage 240NextDC M3 Stage 1 — Completed, 27 MWNextDC M3 Stage 127Macquarie Technology IC3 Super West — Construction, 47 MWMacquarie Technology IC3 Super West47CDC BK1 — Completed, 150 MWCDC BK1150CDC BK2 — Completed, 150 MWCDC BK2150CDC BK3 — Approved, 100 MWCDC BK3100AirTrunk SYD3 — Construction, 400 MWAirTrunk SYD3400Equinix SY9x — Completed, 28 MWEquinix SY9x28AWS Project Echidna — Approved, 35 MWAWS Project Echidna35AirTrunk MEL1 Phase 3 — Completed, 40 MWAirTrunk MEL1 Phase 340CDC Maddington Campus — Approved, 200 MWCDC Maddington Campus200CDC BE1 — Completed, 40 MWCDC BE140STACK Infrastructure MEL01A — Completed, 36 MWSTACK Infrastructure MEL01A36Stockland Khartoum Road — Approved, 76 MWStockland Khartoum Road76NextDC S4 Phase 1 — Construction, 250 MWNextDC S4 Phase 1250Goodman SYD01 — Construction, 81 MWGoodman SYD0181Goodman Project Pluto — Approved, 100 MWGoodman Project Pluto100CDC Marsden Park Campus — Approved, 504 MWCDC Marsden Park Campus504Goodman Project Duke — Approved, 120 MWGoodman Project Duke120Goodman Project Apollo — Approved, 135 MWGoodman Project Apollo135CDC Laverton Campus — Construction, 400 MWCDC Laverton Campus400AirTrunk MEL2 — Approved, 354 MWAirTrunk MEL2354AWS Gregory Hills — Construction, 62 MWAWS Gregory Hills62AirTrunk MEL1 Phase 4 — Completed, 100 MWAirTrunk MEL1 Phase 4100AWS Glendenning Road Campus — Approved, 235 MWAWS Glendenning Road Campus235NextDC M2 Stage 2 — Construction, 60 MWNextDC M2 Stage 260Firmus Project Southgate Stage 1a — Construction, 44 MWFirmus Project Southgate Stage 1a44Firmus Project Southgate Stage 1b — Construction, 46 MWFirmus Project Southgate Stage 1b46NextDC M4 — Approved, 162 MWNextDC M4162DigiCo SYD1 expansion — Approved, 46 MWDigiCo SYD1 expansion46Firmus Bell Bay — Approved, 288 MWFirmus Bell Bay288AirTrunk SYD1 Stage 1 — Approval sought, 4 July 2016 (0 months in)AirTrunk SYD1 Stage 1 — Approval granted, 15 Dec 2016 (5 months in)AirTrunk SYD1 Stage 1 — Construction started, 9 Feb 2017 (7 months in)AirTrunk SYD1 Stage 1 — Completed, 30 Mar 2021 (57 months in)AirTrunk MEL1 Phase 1 — Approval sought, 22 July 2016 (0 months in)AirTrunk MEL1 Phase 1 — Approval granted, 12 Oct 2016 (3 months in)AirTrunk MEL1 Phase 1 — Construction started, 7 Feb 2017 (7 months in)AirTrunk MEL1 Phase 1 — Completed, 16 Mar 2020 (44 months in)NextDC M2 Stage 1 — Construction started, 18 Mar 2017 (0 months in)NextDC M2 Stage 1 — Completed, 21 Feb 2025 (95 months in)AirTrunk SYD2 — Approval sought, 1 Nov 2018 (0 months in)AirTrunk SYD2 — Approval granted, 15 Nov 2019 (12 months in)AirTrunk SYD2 — Construction started, 30 Apr 2020 (18 months in)AirTrunk SYD2 — Completed, 30 Apr 2024 (66 months in)NextDC S3 — Approval sought, 2 Apr 2019 (0 months in)NextDC S3 — Approval granted, 17 Dec 2019 (9 months in)NextDC S3 — Construction started, 30 Mar 2021 (24 months in)NextDC S3 — Completed, 30 June 2023 (51 months in)CDC EC3-EC6 — Approval sought, 9 May 2019 (0 months in)CDC EC3-EC6 — Approval granted, 14 July 2020 (14 months in)CDC EC3-EC6 — Construction started, 30 Mar 2021 (23 months in)CDC EC3-EC6 — projected completion was 6 Feb 2023, now overdue (median 22 months from construction started, n=15)DCI Data Centers SYD01 / SYD02 — Approval sought, 12 Sept 2019 (0 months in)DCI Data Centers SYD01 / SYD02 — Approval granted, 16 Nov 2020 (14 months in)DCI Data Centers SYD01 / SYD02 — Construction started, 29 Feb 2024 (54 months in)DCI Data Centers SYD01 / SYD02 — Completed, 30 Oct 2024 (62 months in)AirTrunk MEL1 Phase 2 — Approval sought, 26 Sept 2019 (0 months in)AirTrunk MEL1 Phase 2 — Approval granted, 7 Nov 2019 (1 months in)AirTrunk MEL1 Phase 2 — Construction started, 16 Mar 2020 (6 months in)AirTrunk MEL1 Phase 2 — Completed, 23 Jan 2022 (28 months in)AirTrunk SYD1 Stage 2 — Approval sought, 22 Nov 2019 (0 months in)AirTrunk SYD1 Stage 2 — Approval granted, 26 Mar 2020 (4 months in)AirTrunk SYD1 Stage 2 — Construction started, 30 Mar 2021 (16 months in)AirTrunk SYD1 Stage 2 — Completed, 30 May 2022 (30 months in)NextDC M3 Stage 1 — Approval sought, 30 Oct 2020 (0 months in)NextDC M3 Stage 1 — Approval granted, 23 Feb 2021 (4 months in)NextDC M3 Stage 1 — Construction started, 2 Dec 2021 (13 months in)NextDC M3 Stage 1 — Completed, 10 Oct 2022 (23 months in)Macquarie Technology IC3 Super West — Approval sought, 14 July 2021 (0 months in)Macquarie Technology IC3 Super West — Approval granted, 19 Jan 2024 (30 months in)Macquarie Technology IC3 Super West — Construction started, 29 Feb 2024 (32 months in)Macquarie Technology IC3 Super West — Completed, 30 July 2026 (61 months in)CDC BK1 — Approval sought, 15 Oct 2021 (0 months in)CDC BK1 — Approval granted, 21 June 2022 (8 months in)CDC BK1 — Construction started, 26 Dec 2022 (14 months in)CDC BK1 — Completed, 23 June 2024 (32 months in)CDC BK2 — Approval sought, 15 Oct 2021 (0 months in)CDC BK2 — Approval granted, 21 June 2022 (8 months in)CDC BK2 — Construction started, 23 June 2024 (32 months in)CDC BK2 — Completed, 1 Mar 2026 (53 months in)CDC BK3 — Approval sought, 15 Oct 2021 (0 months in)CDC BK3 — Approval granted, 21 June 2022 (8 months in)CDC BK3 — projected completion was 12 June 2025, now overdue (median 36 months from approval granted, n=12)AirTrunk SYD3 — Approval sought, 26 Apr 2022 (0 months in)AirTrunk SYD3 — Approval granted, 15 Sept 2023 (17 months in)AirTrunk SYD3 — Construction started, 30 Oct 2023 (18 months in)AirTrunk SYD3 — projected completion was 7 Sept 2025, now overdue (median 22 months from construction started, n=15)Equinix SY9x — Completed, 13 June 2022 (0 months in)AWS Project Echidna — Approval sought, 7 Sept 2022 (0 months in)AWS Project Echidna — Approval granted, 5 Apr 2024 (19 months in)AWS Project Echidna — projected completion 28 Mar 2027 (median 36 months from approval granted, n=12)AirTrunk MEL1 Phase 3 — Construction started, 10 Oct 2022 (0 months in)AirTrunk MEL1 Phase 3 — Completed, 22 May 2023 (7 months in)CDC Maddington Campus — Approval sought, 1 Jan 2023 (0 months in)CDC Maddington Campus — Approval granted, 19 Sept 2025 (33 months in)CDC Maddington Campus — Construction started, 8 Feb 2026 (37 months in)CDC Maddington Campus — projected completion 18 Dec 2027 (median 22 months from construction started, n=15)CDC BE1 — Approval sought, 19 May 2023 (0 months in)CDC BE1 — Approval granted, 3 Oct 2023 (5 months in)CDC BE1 — Construction started, 30 Jan 2024 (8 months in)CDC BE1 — Completed, 22 Jan 2026 (32 months in)STACK Infrastructure MEL01A — Completed, 22 Aug 2023 (0 months in)Stockland Khartoum Road — Approval sought, 10 Oct 2023 (0 months in)Stockland Khartoum Road — Approval granted, 11 Mar 2026 (29 months in)Stockland Khartoum Road — projected completion 2 Mar 2029 (median 36 months from approval granted, n=12)NextDC S4 Phase 1 — Approval sought, 23 Oct 2023 (0 months in)NextDC S4 Phase 1 — Approval granted, 24 Dec 2025 (26 months in)NextDC S4 Phase 1 — Construction started, 25 Mar 2026 (29 months in)NextDC S4 Phase 1 — projected completion 1 Feb 2028 (median 22 months from construction started, n=15)Goodman SYD01 — Approval sought, 21 Dec 2023 (0 months in)Goodman SYD01 — Approval granted, 11 Apr 2025 (16 months in)Goodman SYD01 — Construction started, 5 May 2026 (28 months in)Goodman SYD01 — projected completion 13 Mar 2028 (median 22 months from construction started, n=15)Goodman Project Pluto — Approval sought, 28 Mar 2024 (0 months in)Goodman Project Pluto — Approval granted, 23 July 2026 (28 months in)Goodman Project Pluto — projected completion 14 July 2029 (median 36 months from approval granted, n=12)CDC Marsden Park Campus — Approval sought, 16 May 2024 (0 months in)CDC Marsden Park Campus — Approval granted, 27 Nov 2025 (18 months in)CDC Marsden Park Campus — projected completion 18 Nov 2028 (median 36 months from approval granted, n=12)Goodman Project Duke — Approval sought, 29 May 2024 (0 months in)Goodman Project Duke — Approval granted, 22 Dec 2025 (19 months in)Goodman Project Duke — projected completion 13 Dec 2028 (median 36 months from approval granted, n=12)Goodman Project Apollo — Approval sought, 2 Aug 2024 (0 months in)Goodman Project Apollo — Approval granted, 2 Sept 2026 (25 months in)Goodman Project Apollo — projected completion 24 Aug 2029 (median 36 months from approval granted, n=12)CDC Laverton Campus — Approval sought, 2 Oct 2024 (0 months in)CDC Laverton Campus — Approval granted, 1 Feb 2025 (4 months in)CDC Laverton Campus — Construction started, 21 Feb 2025 (5 months in)CDC Laverton Campus — projected completion 31 Dec 2026 (median 22 months from construction started, n=15)AirTrunk MEL2 — Approval sought, 20 Dec 2024 (0 months in)AirTrunk MEL2 — Approval granted, 28 Mar 2025 (3 months in)AirTrunk MEL2 — projected completion 19 Mar 2028 (median 36 months from approval granted, n=12)AWS Gregory Hills — Approval sought, 7 Feb 2025 (0 months in)AWS Gregory Hills — Approval granted, 21 Nov 2025 (9 months in)AWS Gregory Hills — Construction started, 25 July 2026 (18 months in)AWS Gregory Hills — projected completion 2 June 2028 (median 22 months from construction started, n=15)AirTrunk MEL1 Phase 4 — Construction started, 21 Feb 2025 (0 months in)AirTrunk MEL1 Phase 4 — Completed, 10 Feb 2026 (12 months in)AWS Glendenning Road Campus — Approval sought, 21 Mar 2025 (0 months in)AWS Glendenning Road Campus — Approval granted, 14 Sept 2026 (18 months in)AWS Glendenning Road Campus — projected completion 5 Sept 2029 (median 36 months from approval granted, n=12)NextDC M2 Stage 2 — Approval sought, 23 Apr 2025 (0 months in)NextDC M2 Stage 2 — Approval granted, 25 Sept 2025 (5 months in)NextDC M2 Stage 2 — Construction started, 1 Jan 2026 (8 months in)NextDC M2 Stage 2 — projected completion 10 Nov 2027 (median 22 months from construction started, n=15)Firmus Project Southgate Stage 1a — Approval granted, 1 Sept 2025 (0 months in)Firmus Project Southgate Stage 1a — Construction started, 11 Dec 2025 (3 months in)Firmus Project Southgate Stage 1a — projected completion 20 Oct 2027 (median 22 months from construction started, n=15)Firmus Project Southgate Stage 1b — Approval granted, 1 Sept 2025 (0 months in)Firmus Project Southgate Stage 1b — projected completion 23 Aug 2028 (median 36 months from approval granted, n=12)NextDC M4 — Approval sought, 23 Oct 2025 (0 months in)NextDC M4 — Approval granted, 16 Jan 2026 (3 months in)NextDC M4 — projected completion 7 Jan 2029 (median 36 months from approval granted, n=12)DigiCo SYD1 expansion — Approval granted, 23 Dec 2025 (0 months in)DigiCo SYD1 expansion — projected completion 14 Dec 2028 (median 36 months from approval granted, n=12)Firmus Bell Bay — Approval sought, 13 June 2026 (0 months in)Firmus Bell Bay — Approval granted, 25 Aug 2026 (2 months in)Firmus Bell Bay — projected completion 16 Aug 2029 (median 36 months from approval granted, n=12)
Ordered by the date an application was first lodged; where none is on record, by the earliest milestone that is. Excludes 44 projects under 20 MW and 14 with an application and nothing since. Dates to 23 Sept 2026. Projections carry each of the 22 unfinished projects forward from the stage it is at by the median time to completion observed among the 17 completed projects here — 47 months from approval sought (n=12), 36 months from approval granted (n=12), 22 months from construction started (n=15). 3 projections have already passed without the project completing; those are pinned to today and drawn hollow.